Bali to tackle electrical faults September-November
The National Electricity Board (PLN) has warned that Bali may have blackouts for the period between the dates of September 23 – November 23, 2009, as repairs are undertaken in an electric power plant gas Gilimanuk near the price in the West Bali
As reported by the Jakarta Post, are warning consumers that the key areas of Kuta, the SAD of Denpasar and Nusa be experiencing blackouts of several hours each day during the specified period.
While PLN are renting additional energy generators to help reduce the need for blackouts. When operating at full capacity, PLN Bali 562 mega watts provides energy at a peak hour demand of 490 megawatts. The remedy provided in the station gnerating of Bali Gilimanuk reduced the ‘s the source of only 432 megawatt, low supply throughout the island’s demand for energy at peak times.
Bali ‘power supply comes from a power plant’s diesel-generated Pesanggaran (152 megawatts), Pemaron (80 megawatts), the Java-Bali interconnection (200 MW) and Gilimanuk (130 megawatts).